banner ad
Experts Logo

articles

Construction Claims For Variation in Quantity

By: Long International, Inc. - Richard J. Long
Tel: (303) 972-2443
Email Mr. Long or Mr. Avalon


View Profile on Experts.com.


1. Introduction

A component of a construction claim often relates to the cost, quantity, and quality of the materials that the contractor installed on a project. The contractor frequently purchases these materials and agrees to install the quantities of materials on a unit price basis, i.e., a unit price that includes both the cost of the materials and the cost to install them. The parties may contemplate some minor variations in such quantities from the contract estimate, especially if the engineering documents are not issued "Approved for Construction (AFC)." Even when AFC drawings are issued prior to establishing the contract price, changes may occur which may cause deviations from the approved design which could significantly increase or decrease the required quantities to be installed and the contractor's costs.

Unit price contracts are often used to shorten the overall duration of a project because a detailed design from which final quantity takeoffs can be performed is not necessary to enable a contractor and owner to agree on a contract to perform the construction work. Thus, field construction work can start earlier than would otherwise be required in a traditional engineering, procurement, construction (EPC) contract or design-build contract, where a more precise measure of quantities is necessary to obtain a lump-sum or fixed-price bid from a contractor. Under a unit price contract, a contractor typically buys material, adds a mark-up for overhead and profit, and agrees to perform the work for this unit price. Of prime importance to the contractor is whether its unit prices are sufficient to cover its overhead and other costs if the number of units significantly changes from the estimated quantities used to prepare its bid. If the owner's estimated quantities are higher than the quantities that are actually required, the contractor may have a claim for unrecovered overhead costs and profit.

An owner, often in an effort to realize cost savings as a result of value engineering, may change the design, reduce the quantities specification, and request a credit from the contractor. However, the contractor might not pass on the full savings it achieved from the owner's change, potentially causing a dispute with the owner who is expecting a larger credit.

Contractors also take risks with unit price contracts. The contractor may tactically apply its overhead and profit percentages in an unbalanced manner to items for which it expects large quantity increases as the design matures, thus receiving an additional layer of profit. As stated by one court:

Such a bid, it is explained, is one in which the contractor allocates a disproportionate share of indirect costs and anticipated profit to the unit prices bid for those items on which he anticipates an overrun; the object being to reap over generous profits should the anticipated overruns materialize

Such practices could backfire if the quantities of "over-priced" items do not materially increase or, even worse, decrease as a result of value engineering, thus reducing the contractor's recovery of overhead and profit.

2. VARIATION IN QUANTITY CLAUSES

. . .Continue to read rest of article (PDF).


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

stanley-Stephenson-Photo.jpg

1/30/2013· Construction

Building Defects Can Derail Your Deal

By: Dr. Stanley Stephenson

Defects introduced in construction can lead to classic legal disputes between owners and contractors, especially when considerable sums of money are involved. What can a commercial mortgage broker learn from these disputes? What risks and potential rewards might arise?

Thomas-Barth-Crane-Logo.jpg

7/31/2015· Construction

Tower Cranes Warrant Closer Look

By: Thomas Barth

According to statistics, about 125,000 tower cranes are operating worldwide and, on average, are erected in 2 days on various jobsites to build skyscrapers. There are two types of cranes, tower and mobile, which can be purchased or rented depending on the company's scope of work. Mobile cranes are limited because they must be moved from location to location on the jobsite to maneuver materials. Tower cran es can be placed closer toge ther, have a radius of about 140 square meters, and can lift steel, concrete, and a va riable range of building material. Contractors can save 50 percent on the cost of material handling by using self-erecting tower cranes and onsite labor, saving thousands. Due to the flexibility of tower cranes, they are becoming more commercialized and are high in demand.

wayne_baruch_logo.jpg

5/25/2011· Construction

Lead Based Paint: Compliance With EPA's RRP Rule (40 CFR 745); Renovation, Repair, And Painting...And The Real World

By: Wayne Baruch

By now, you have probably heard about the rules that tell us how to properly manage lead-based paint under the U.S. EPA, the U.S. Dept. of Housing and Urban Development (HUD), the Occupational Health and Safety Administration (OSHA), and most State, County, and Local governments.

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;