Your browser is currently set to block JavaScript.

For full functionality of this site it is necessary to enable JavaScript. Here are the instructions how to enable JavaScript in your web browser.

After enabling javascript, please refresh the page to go back to experts.com site with full functionality

Would you turn off/on JavaScript?

It's a widely used language that makes the web what it is today, allowing for websites to be more responsive, dynamic, and interactive. Disabling JavaScript takes websites back to a time when they were simple documents without any other features.

What are the advantages of using JavaScript?

Speed. Since JavaScript is an 'interpreted' language, it reduces the time required by other programming languages like Java for compilation. JavaScript is also a client-side script, speeding up the execution of the program as it saves the time required to connect to the server.

banner ad
Experts Logo

articles

Construction Contract Notice Letters

By: Richard J. Long, P.E., P.Eng.
Tel: (303) 972-2443
Email: Long International, Inc.


View Profile on Experts.com.


Background

Most construction contracts require written notice for changes, differing site conditions, extra work, or other events which may affect the contractor’s time and cost of performance. The process of giving “notice” is vital to triggering the contract mechanisms that allow the contractor to pursue additional time and cost and to reserve its rights to recover for any unforeseen but related impacts that may later arise.

As discussed in a recent Long International article, The Importance and Value of “Notice” Provisions in Construction Contracts,1 failure to provide proper and timely notice may limit the contractor’s ability to recover its increased costs of performance. Some of the key factors required by standard contract form notice provisions are as follows:

  1. Notice must be in writing;
  2. Written notice must be served to a specific designated party;
  3. Notice must be given as soon as the notifying party becomes aware of the circumstances of an impact event or condition;
  4. Notice must be given within a defined time period;
  5. Notice for time and additional cost impacts must be given if both are deemed involved;
  6. Details of the actual or anticipated effects of any impacts, if practicable;
  7. Estimates of the extent of any time and cost impact;
  8. Supporting documentation must be submitted within a specified time frame (possible second notice period);
  9. Specific schedule and work activities affected; and
  10. Cause, effect, and length.

All of the contractually required information associated with a notice, as listed above, may not be immediately available when the event triggering a requirement for a notice occurs. A timely notice should still be provided regarding the event or problem with an indication that more detailed information will be provided at a later date.

To facilitate their preparation, sample notice letters are provided for the following events:

  • Constructive change for additional work
  • Nonpayment
  • Directed acceleration
  • Access delay
  • Late or defective owner-furnished equipment or materials
  • Differing site conditions
  • Change directive
  • Claim for extras in advance of work being performed
  • Claim for extras after work was performed
  • Request for extension of time and additional compensation
  • Multiple problems
  • Noncompliance notice to subcontractor
  • Change order proposal transmittal letter
  • Change order execution transmittal letter
  • Request for time extension due to severe weather
  • Request for CPM data if owner or construction manager is maintaining the schedule

  • . . . Download PDF article to view sample notice letters.

Should you have any questions regarding the issue of notice or the sample letters below, please contact Richard J. Long at (303) 972-2443


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

Richard J. Long, P.E., is Founder and CEO of Long International, Inc. Mr. Long has over 40 years of U.S. and international engineering, construction, and management consulting experience involving construction contract disputes analysis and resolution, arbitration and litigation support and expert testimony, project management, engineering and construction management, cost and schedule control, and process engineering. As an internationally recognized expert in the analysis and resolution of complex construction disputes for over 30 years, Mr. Long has served as the lead expert on over 300 projects having claims ranging in size from US $100,000 to over US $2 billion. He has presented and published numerous articles on the subjects of claims analysis, entitlement issues, CPM schedule and damages analyses, and claims prevention. Mr. Long earned a B.S. in Chemical Engineering from the University of Pittsburgh in 1970 and an M.S. in Chemical and Petroleum Refining Engineering from the Colorado School of Mines in 1974.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

coleman-horowitt-logo.jpg

6/21/2018· Construction

Court Determines Sanitary District Can Use Its Own Employees for Construction Projects

By: Darryl Horowitt

The Public Contracts Code generally provides that contracts for certain dollar amounts, generally exceeding $15,000 to $25,000, must be sent out for bid and let to the lowest responsible bidder after appropriate notice is given. Public Contracts Code § 20803, which governs sanitary districts, contains such a requirement for any contract exceeding $15,000.

long-international-logo.jpg

4/13/2012· Construction

Construction Disputes: Schedule and Delay Analysis Methodologies

By: Long International

The equitable allocation of responsibility for project delays is essential to the resolution of many construction disputes. Contractors frequently assert that they have been delayed for reasons beyond their control. Owners often remain unconvinced that the Contractor is legitimately entitled to a time extension or delay, acceleration and loss of productivity damages.

Jeffrey-Weinstein-Architect-Construction-Management-Expert-Photo.jpg

9/11/2017· Construction

Common Sense Strategies for Avoiding Construction Litigation

By: Jeffrey P. Weinstein

ln our current climate of economic prosperity and rising real estate values, the prevalence and usefulness of construction litigation may be on the wane. Much of the litigation and expert opinion in recent years has resulted in unrealistic repair schemes for the sole purpose of producing a settlement among parties to the litigation. When a plaintiff expert recommends a "remove and replace in its entirety"1 scenario (for example, arguing that all exterior stucco must be demolished and reinstalled due to a lack of expansion joints), the defense expert frequently advocates a more modest "fix what's broken" scheme to provide a minimum repair at the lowest cost. This process consumes considerable time and resources, and creates a difficult environment in which to craft a settlement. More often than not, neither party is pleased with the outcome; unreasonable plaintiff positions often result in settlement amounts ranging between 15 to 25 percent of the claim amount.

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;