Your browser is currently set to block JavaScript.

For full functionality of this site it is necessary to enable JavaScript. Here are the instructions how to enable JavaScript in your web browser.

After enabling javascript, please refresh the page to go back to experts.com site with full functionality

Would you turn off/on JavaScript?

It's a widely used language that makes the web what it is today, allowing for websites to be more responsive, dynamic, and interactive. Disabling JavaScript takes websites back to a time when they were simple documents without any other features.

What are the advantages of using JavaScript?

Speed. Since JavaScript is an 'interpreted' language, it reduces the time required by other programming languages like Java for compilation. JavaScript is also a client-side script, speeding up the execution of the program as it saves the time required to connect to the server.

banner ad
Experts Logo

articles

The Collapsed As-Built Windows Schedule Analysis Method

By: Long International, Inc. - Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA
Tel: (303) 972-2443
Email:Mr. Avalon


View Profile on Experts.com.


ABSTRACT

The Collapsed As-Built Windows Schedule Analysis (AACE® International Recommended Practice 29R-03, Method Implementation Protocol 3.9) is a modeled, subtractive, multiple-base method. It is a retrospective CPM schedule analysis which is typically used to prove entitlement for compensable delay and assess concurrency of delay within a window of time. The analysis simulates the as-built conditions within a schedule window and then delays are removed from the CPM model. If the forecasted project finish date "collapses" but-for or absent compensable delays, then entitlement for compensable time-related costs can be demonstrated. This article addresses the usage of the Collapsed As-Built Windows protocol and the advantages and disadvantages of the methodology.

1. INTRODUCTION

It is common that an unanticipated event or issue may cause delay and extend the overall completion of a project. It is also common that project stakeholders may dispute the responsibility for a project issue that caused delay and extended the overall completion of a project. A project issue can become contested, cause multiple delays, affect several areas of a project, occur at different points in time, and become intertwined with non-contested issues. To achieve an equitable resolution of a contested project issue that caused delay, it is imperative for an analyst to answer the following basic questions:

  • Who caused the delay?
  • Why did the delay occur?
  • What impact did the delay cause?
  • Where did the delay occur?
  • When did the delay occur?

On large and complex projects, the process of evaluating delay issues is further complicated when the schedule file is comprised of numerous process areas/units, thousands of activities with activity groups spanning many months or years, and multiple critical and near-critical paths. One retrospective forensic schedule analysis that can be used to evaluate concurrency and quantify compensable delay is the Collapsed As-Built schedule analysis method applied on a windows basis (AACE® International Recommended Practice 29R-03, MIP 3.9).

2. THE COLLAPSED AS-BUILT WINDOWS ANALYSIS DEFINED


. . .Continue to read rest of article (PDF).


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

coleman-horowitt-logo.jpg

6/21/2018· Construction

Court Determines Sanitary District Can Use Its Own Employees for Construction Projects

By: Darryl Horowitt

The Public Contracts Code generally provides that contracts for certain dollar amounts, generally exceeding $15,000 to $25,000, must be sent out for bid and let to the lowest responsible bidder after appropriate notice is given. Public Contracts Code § 20803, which governs sanitary districts, contains such a requirement for any contract exceeding $15,000.

long-international-logo.jpg

9/27/2013· Construction

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

By: Long International

The "discrete damages/cost variance analysis method" for quantifying construction claim damages involves the specific distribution of all costs incurred on the project rather than quantifying only certain parts of the cost or damage analysis as may be used in the other methods.

long-international-logo.jpg

9/4/2013· Construction

Developing Subcontract Pricing As Applied to Building Construction

By: Long International

ABSTRACT - This paper provides guidelines to commercial construction cost engineers for the development of a plan for obtaining and utilizing subcontractor cost information for use in bidding, procurement, scheduling, change order management, and claim management. The paper is based upon personal field experience gained in cost engineering, scheduling, bidding, planning, contracting, and claim analyses.

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;