banner ad
Experts Logo

articles

The Collapsed As-Built Windows Schedule Analysis Method

By: Long International, Inc. - Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA
Tel: (303) 972-2443
Email:Mr. Avalon


View Profile on Experts.com.


ABSTRACT

The Collapsed As-Built Windows Schedule Analysis (AACE® International Recommended Practice 29R-03, Method Implementation Protocol 3.9) is a modeled, subtractive, multiple-base method. It is a retrospective CPM schedule analysis which is typically used to prove entitlement for compensable delay and assess concurrency of delay within a window of time. The analysis simulates the as-built conditions within a schedule window and then delays are removed from the CPM model. If the forecasted project finish date "collapses" but-for or absent compensable delays, then entitlement for compensable time-related costs can be demonstrated. This article addresses the usage of the Collapsed As-Built Windows protocol and the advantages and disadvantages of the methodology.

1. INTRODUCTION

It is common that an unanticipated event or issue may cause delay and extend the overall completion of a project. It is also common that project stakeholders may dispute the responsibility for a project issue that caused delay and extended the overall completion of a project. A project issue can become contested, cause multiple delays, affect several areas of a project, occur at different points in time, and become intertwined with non-contested issues. To achieve an equitable resolution of a contested project issue that caused delay, it is imperative for an analyst to answer the following basic questions:

  • Who caused the delay?
  • Why did the delay occur?
  • What impact did the delay cause?
  • Where did the delay occur?
  • When did the delay occur?

On large and complex projects, the process of evaluating delay issues is further complicated when the schedule file is comprised of numerous process areas/units, thousands of activities with activity groups spanning many months or years, and multiple critical and near-critical paths. One retrospective forensic schedule analysis that can be used to evaluate concurrency and quantify compensable delay is the Collapsed As-Built schedule analysis method applied on a windows basis (AACE® International Recommended Practice 29R-03, MIP 3.9).

2. THE COLLAPSED AS-BUILT WINDOWS ANALYSIS DEFINED


. . .Continue to read rest of article (PDF).


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

Thomas-Barth-Crane-Logo.jpg

10/23/2015· Construction

Crane Training Lacking In U.S.: Other Countries Lead the Way to Safety

By: Thomas Barth

Here in the United States our crane training program is falling through the cracks. Other countries, such as Canada, have one of the best training programs in the world. The United States tried to put a program together by copying their program but unfortunately they left out the most valuable parts.

Thomas-Barth-Crane-Logo.jpg

7/31/2015· Construction

Tower Cranes Warrant Closer Look

By: Thomas Barth

According to statistics, about 125,000 tower cranes are operating worldwide and, on average, are erected in 2 days on various jobsites to build skyscrapers. There are two types of cranes, tower and mobile, which can be purchased or rented depending on the company's scope of work. Mobile cranes are limited because they must be moved from location to location on the jobsite to maneuver materials. Tower cran es can be placed closer toge ther, have a radius of about 140 square meters, and can lift steel, concrete, and a va riable range of building material. Contractors can save 50 percent on the cost of material handling by using self-erecting tower cranes and onsite labor, saving thousands. Due to the flexibility of tower cranes, they are becoming more commercialized and are high in demand.

Sanford-Loy-Construction-Defect-Expert-Photo.jpg

12/14/2022· Construction

Design-Bid-Build, Design-Build Or Construction Management? Circa 2022

By: Sanford C. Loy

Any of these methods can produce beneficial results…but the decision as to which one is used must be made carefully with a full understanding of the pluses and minuses of each; each owner’s circumstances, risk tolerance, staffing, experience with construction, the degree to which the schedule and budget are respectively critical as well a

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;