5/28/2013· Construction
Assessing Damages Arising From Construction Defects
Defects that were introduced during construction can lead to classic legal disputes between owners and contractors where considerable sums of money are involved.
By: Long International, Inc. - Richard Long P.E.
Tel: (303) 972-2443
Email:Long International, Inc.
Time is money especially on engineering and construction projects. Because delays in the completion of the project usually result in increased owner, engineer, and contractor costs, the overall time of performance is vital to the financial success of the project. The importance of time is evidenced by the significant role played by CPM schedules, completion dates, and milestones in the bidding and awarding of engineering and construction contracts. The desire to minimize costs and the time of performance often causes the occurrence of acceleration.
This article discusses the following topics:1
There are three types of acceleration: directed acceleration, constructive acceleration, and voluntary acceleration.
Directed acceleration occurs when the owner or construction manager issues a specific order to its construction contractor under the contract provisions to 1) complete the project earlier than the originally scheduled completion date, 2) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to complete the base contract work plus additional or changed work within the original contract time,2 or 3) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to make-up for contractor-caused delays that threaten the on-time completion of the project. These measures can result in costs being incurred that would not otherwise have been required.
Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.
©Copyright - All Rights Reserved
DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.
5/28/2013· Construction
Assessing Damages Arising From Construction Defects
Defects that were introduced during construction can lead to classic legal disputes between owners and contractors where considerable sums of money are involved.
5/17/2021· Construction
Analysis Of Concurrent Delay On Construction Claims
Concurrent delay is a vexed and complex technical and legal issue. Construction contracts often do not expressly provide direction as to the parties’ agreement when there is concurrent delay. Most simply require the contractor to provide notice and specifics when an owner-responsible delay event occurs.
4/3/2015· Construction
Unfairly Blaming Tenants for Interior Mold?
By: Lonnie Haughton
Who likely should be blamed for the blackish mold growth found at this new three-bedroom, two-bath apartment in San Jose, California? Unfortunately, landlords often rush to accuse their tenants of generating too much "lifestyle moisture". In many cases, such assessments are both inaccurate and unfair.