banner ad
Experts Logo

articles

Acceleration Claims on Engineering and Construction Projects

By: Long International, Inc. - Richard Long P.E.
Tel: (303) 972-2443
Email:Long International, Inc.


View Profile on Experts.com.


1. INTRODUCTION

Time is money especially on engineering and construction projects. Because delays in the completion of the project usually result in increased owner, engineer, and contractor costs, the overall time of performance is vital to the financial success of the project. The importance of time is evidenced by the significant role played by CPM schedules, completion dates, and milestones in the bidding and awarding of engineering and construction contracts. The desire to minimize costs and the time of performance often causes the occurrence of acceleration.

This article discusses the following topics:1

  • Types of Acceleration;
  • Key Elements of Acceleration Required by the Courts;
  • Acceleration Claims Outside of the United States;
  • Notice Requirements;
  • The Relevance of the Date When the Time Extension Is Given;
  • Contract Provisions Associated with Acceleration;
  • The Effect of a "No Damage For Delay" Clause on Acceleration;
  • Identifying Acceleration Using the Project Schedules;
  • Documenting Acceleration Evidence; and
  • Acceleration Damages.

2. TYPES OF ACCELERATION

There are three types of acceleration: directed acceleration, constructive acceleration, and voluntary acceleration.

Directed acceleration occurs when the owner or construction manager issues a specific order to its construction contractor under the contract provisions to 1) complete the project earlier than the originally scheduled completion date, 2) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to complete the base contract work plus additional or changed work within the original contract time,2 or 3) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to make-up for contractor-caused delays that threaten the on-time completion of the project. These measures can result in costs being incurred that would not otherwise have been required.

. . .Continue to read rest of article (PDF).


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

Jeffrey-Weinstein-Architect-Construction-Management-Expert-Photo.jpg

9/11/2017· Construction

Common Sense Strategies for Avoiding Construction Litigation

By: Jeffrey P. Weinstein

ln our current climate of economic prosperity and rising real estate values, the prevalence and usefulness of construction litigation may be on the wane. Much of the litigation and expert opinion in recent years has resulted in unrealistic repair schemes for the sole purpose of producing a settlement among parties to the litigation. When a plaintiff expert recommends a "remove and replace in its entirety"1 scenario (for example, arguing that all exterior stucco must be demolished and reinstalled due to a lack of expansion joints), the defense expert frequently advocates a more modest "fix what's broken" scheme to provide a minimum repair at the lowest cost. This process consumes considerable time and resources, and creates a difficult environment in which to craft a settlement. More often than not, neither party is pleased with the outcome; unreasonable plaintiff positions often result in settlement amounts ranging between 15 to 25 percent of the claim amount.

michael-panish-logo.gif

2/18/2015· Construction

M. O. A. T. A New Approach to School Security

By: Michael Panish

The need to have increased security to public venues such as airports, schools, religious facilities, day care centers, shopping centers, and government buildings is nothing new. However, it has become apparent that many unexpected assaults and deadly attacks are coming from individuals that have gained a certain level of intimacy with the venues and organizations that they are invading. The attackers are not necessarily strangers, but people we know.

richard_long_photo.jpg

5/17/2021· Construction

Analysis Of Concurrent Delay On Construction Claims

By: Long International

Concurrent delay is a vexed and complex technical and legal issue. Construction contracts often do not expressly provide direction as to the parties’ agreement when there is concurrent delay. Most simply require the contractor to provide notice and specifics when an owner-responsible delay event occurs.

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;