banner ad
Experts Logo

articles

Acceleration Claims on Engineering and Construction Projects

By: Long International, Inc. - Richard Long P.E.
Tel: (303) 972-2443
Email:Long International, Inc.


View Profile on Experts.com.


1. INTRODUCTION

Time is money especially on engineering and construction projects. Because delays in the completion of the project usually result in increased owner, engineer, and contractor costs, the overall time of performance is vital to the financial success of the project. The importance of time is evidenced by the significant role played by CPM schedules, completion dates, and milestones in the bidding and awarding of engineering and construction contracts. The desire to minimize costs and the time of performance often causes the occurrence of acceleration.

This article discusses the following topics:1

  • Types of Acceleration;
  • Key Elements of Acceleration Required by the Courts;
  • Acceleration Claims Outside of the United States;
  • Notice Requirements;
  • The Relevance of the Date When the Time Extension Is Given;
  • Contract Provisions Associated with Acceleration;
  • The Effect of a "No Damage For Delay" Clause on Acceleration;
  • Identifying Acceleration Using the Project Schedules;
  • Documenting Acceleration Evidence; and
  • Acceleration Damages.

2. TYPES OF ACCELERATION

There are three types of acceleration: directed acceleration, constructive acceleration, and voluntary acceleration.

Directed acceleration occurs when the owner or construction manager issues a specific order to its construction contractor under the contract provisions to 1) complete the project earlier than the originally scheduled completion date, 2) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to complete the base contract work plus additional or changed work within the original contract time,2 or 3) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to make-up for contractor-caused delays that threaten the on-time completion of the project. These measures can result in costs being incurred that would not otherwise have been required.

. . .Continue to read rest of article (PDF).


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

wayne_baruch_logo.jpg

11/18/2011· Construction

Consumer Protection & More Successful Construction Projects (We're In It Together)

By: Wayne Baruch

Owners, consumers, professionals, tradespeople, vendors, and regulators are all involved in the purchase goods and services. However, how many are actually, accurately aware of their duties and rights for those transactions according to the law? Some parties are ethical and/or competent to make a wise purchase.

long-international-logo.jpg

12/4/2023· Construction

Schedule Optimization During Front-End Planning

By: Long International

This paper summarizes the development and review steps of project plans and schedules during the front-end planning phases, including the critical phase of Front-End Engineering Design (FEED). The project milestones, resources, and completion dates established during FEED set the baseline control plan during project execution.

richard_long_photo.jpg

5/17/2021· Construction

Analysis Of Concurrent Delay On Construction Claims

By: Long International

Concurrent delay is a vexed and complex technical and legal issue. Construction contracts often do not expressly provide direction as to the parties’ agreement when there is concurrent delay. Most simply require the contractor to provide notice and specifics when an owner-responsible delay event occurs.

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;