1. INTRODUCTION
The equitable  allocation of responsibility for  project delays is essential to the resolution of many construction disputes. Contractors frequently assert that they  have been delayed for reasons beyond their control. Owners often remain unconvinced that the Contractor is  legitimately entitled to a time extension or delay, acceleration and loss of productivity damages. Large dollar amounts may hinge upon the outcome  of a dispute over project  delay. Consequently, a thorough retrospective schedule analysis  of all project delays is essential for the equitable resolution of delay and  impact-related construction disputes.
Most  construction contracts allow the Owner to recover either liquidated or actual  damages for delay caused by the Contractor.  Contractors also may be contractually entitled  to recover:
  - extended  field  and  home  office  overhead  costs  because  of  Owner-caused  delays,
 
  - acceleration and disruption costs if the Owner fails to  approve valid time extension requests, and 3) loss of productivity costs if  delays caused by changes in scope, events beyond the Contractor’s control, or  the Owner’s interference disrupt and negatively impact the Contractor’s planned  sequence and efficiency of performing its work. However, the Contractor’s actions as well as the actions of its subcontractors, vendors, and suppliers may also cause delay, disruption, and impact to the Contractor’s planned performance. Therefore, a retrospective schedule  analysis must evaluate the contractual obligations and rights of each party.
 
The  retrospective schedule analyses performed by Long International typically focus  on comparing as-planned, updated and as-built project schedules to identify and  quantify delays to the critical and near critical paths of the project. These delays may include either variances  in the duration of an activity or variances in the planned and actual  relationship lag durations between predecessor and successor activities. Concurrent delays are also analyzed to  properly understand the Owner’s and Contractor’s liability for delay and impact  damages. Once all critical and near  critical path activity delays have  been quantified, the origins and causes of each delay are determined. This process often involves the  organization and analysis of extensive project documentation to establish the  cause-effect relationships of each party’s actions or inactions and the resulting delays. The responsibility for each delay is  then apportioned to either the  Contractor, Owner, a third party, if appropriate, and to force majeure or other  excusable delays defined by the contract.
Long International frequently performs “Update  Impacted” and “As-Built But-For” schedule analyses using a windows approach to  evaluate the contemporaneous, cumulative impact of delays caused by each party  on the contractual completion dates. These  two schedule analysis techniques determine the impact of delays during various schedule  windows of time. The project schedule windows are typically  based upon the data dates of the Contractor’s monthly schedule updates when the  critical path may have changed due to key project events. The cumulative results of the analysis of  delays to all schedule windows serve as the basis for an equitable  apportionment of responsibility for delay and impact damages to the project  participants.
In the sections that follow, Long International explains its detailed  schedule analysis methodology using a construction delay claim on a  hypothetical waste water treatment plant project. The fictitious parties  in this example include the Owner, Olympia  Chemical Corporation and the  Contractor, Milestone Construction.
As shown in Figure 1, the Olympia Waste Water Treatment Plant  (WWTP) project was planned to be completed in 502 calendar days. The actual duration, however, was 677  calendar days. Therefore, the net actual delay  was 175 days. An update  impacted and as-built but-for schedule analysis was performed to allocate  responsibility for the 175 days of delay.
The update  impacted analysis adds excusable delays into the schedule update to determine  the cumulative impact of excusable delays to the project completion date. The update impacted analysis determines  the amount of time extension that the Contractor is entitled to claim and the  amount of liquidated damages that the owner is entitled to assess. For the Olympia WWTP project, the update  impacted analysis determined that Milestone Construction is entitled to receive  a time extension of 74 calendar days and Olympia Chemical Corporation is  entitled to assess 101 calendar days of liquidated damages.
The as-built but-for analysis subtracts compensable  delays from the as-built schedule for each schedule window to determine the  earliest date that the Contractor could finish its work absent compensable  delays. The cumulative amount of  compensable delay calculated for all schedule windows using the as-built  but-for analysis represents the total amount of delay for which the Contractor is entitled to recover extended  field and home office overhead  costs. For the Olympia  WWTP project, the as-built but-for  analysis determined that Milestone Construction is entitled to receive compensation for 27 calendar  days of extended overhead costs. 
2. UPDATE IMPACTED ANALYSIS
Long  International’s Update Impacted schedule analysis, as illustrated by Figure 2, adds excusable delays to affected  activities in the Contractor’s schedule update at the start of each schedule window to determine how much time extension the Contractor is entitled to receive as a  result of the excusable delays that occurred during the schedule window. Excusable delays may include compensable delays caused by the Owner such as  change orders, late delivery  of Owner- furnished  equipment, or delayed approvals, or noncompensable delays such as strikes,  unusually severe weather, or governmental actions for which the Contractor may  also be contractually entitled to a time extension, depending on the  contractual terms or case law.
For example,  during each monthly update or schedule window, the Contractor may have  experienced approved scope changes. New  activities may have been added to the schedule updates to account for the new  work associated with the approved changes, or the Contractor may have increased  the duration of existing activities to show the effect of the increased work  scope. The delays to each activity  affected by the changed work are typically quantified by making estimates of  the additional time required to perform the changed work or by including any  time extension agreed in the approved change order into the critical path  leading to project completion. A  comparison of the actual activity durations and relationship lag durations that  occurred in the as-built schedule at the end of the schedule window to the  forecasted activity durations and relationship lag durations at the beginning of  the schedule window may also be used to quantify  the delay. However, Contractor-caused delays  included in the activity  durations or relationship lag durations of the as-built schedule updates  are not included in the time extension calculation.
Changes that  occurred during a schedule window may also affect existing activities beyond  the data date of the schedule window. For  example, if a change order is approved during the engineering phase that will  add additional work to the construction of a piping system in a later schedule  window, the increased duration is added to the affected future construction  activity as part of the analysis of the earlier schedule window when the change  was approved. By adding the excusable  delays to affected schedule activities of the as-planned schedule as they  occur, Long International determines the amount of time extension that would  be required as a result of the  delays. Acceleration paid for by the Owner may reduce activity durations or relationship lag durations and the Contractor’s  entitlement to a time extension. As a  result, the effect of any owner-paid acceleration is also evaluated in Long  International’s schedule analysis.
The sum of the delay results that are calculated in  each schedule window represents the overall time extension for the project. The projected extension in the schedule  completion date compared to the contractually required completion date  represents the amount of time extension that the Contractor is entitled to  receive. For example, the update impacted  analysis for the Olympia WWTP project determined that Milestone Construction is  entitled to 1 calendar day of  excusable delay in Window 1, 39 calendar  days of excusable  delay in Window  2, 27 calendar days of  excusable delay in Window 3 and 7 calendar days of excusable delay in Window  4 for a total of 74 calendar days.
A comparison of the update impacted schedule  completion dates to the as-built schedule actual completion dates, as shown by Figure 2, determines: 1) the amount of Contractor-caused delay in  the as-built schedule that is subject to liquidated damages if the as-built  completion date is later than the update  impacted completion date, or 2) the amount  of acceleration that the Contractor has accomplished if the as-built completion date is earlier  than the update impacted completion date.
3. AS-BUILT BUT-FOR ANALYSIS
Long  International’s As-Built But-For schedule analysis, as shown by Figure 3, determines the earliest date that the  required project completion or Final Acceptance milestone(s) could be achieved  if the compensable delays did not occur. Unlike  analysis of delays to the critical path of the Contractor’s schedule update at the beginning of a schedule window, Long  International’s As-Built But-For schedule analysis quantifies delay  responsibility to activities on the actual critical path of the project that is  calculated at the end of each schedule window.  Because the actual critical path in each schedule window may be different  than the planned critical path at the start of each schedule window, as  illustrated by Figure 4, Long International’s  As-Built But-For schedule analysis focuses on responsibility for delays that  affected the dynamic nature of the actual critical path of the project. For example, at the beginning of Window 3  on the Olympia WWTP project, the as-planned critical  path ran through  piping procurement and installation.  By the end of Window 3, however,  fabrication and delivery delays caused the anaerobic pump installation to  become the as-built critical path.
Long  International quantifies the cumulative effect of compensable delays on the  project completion date by first removing compensable delays caused by the  Owner from the activity durations and relationship lag durations in the  as-built calculation schedule1 for each schedule window and then recalculating the calculation schedule  absent compensable delays. If the  as-built calculation schedule completion date collapses to an earlier  completion date after the Owner-caused compensable delays are removed, the net  duration of the schedule collapse is the amount of compensable delay days for  which the Owner may be liable for the Contractor’s extended field overhead and  home office overhead costs. If the  calculation schedule does not collapse, the Owner-caused delays that were removed were either: 1) not on the critical  path, or 2) concurrent with Contractor-caused delays or other  excusable but noncompensable delays that were also on the as-built critical  path or parallel critical path(s) and prevented the completion date from  collapsing to an earlier date. The  net overall compensable delay at the end of the project is determined by adding the number of  compensable delay days derived from the as-built but-for  calculations in each schedule window. For  example, the as-built but-for analysis for the Olympia WWTP project  determined that Milestone Construction is entitled to  3 calendar days of compensable delay  in Window 1, 20 calendar  days of compensable delay in Window 2, 4 calendar  days of compensable delay in Window 3, and zero calendar days of compensable  delay in Window 4 for a total of 27 calendar days of compensable delay.
4. DETAILED PROCEDURE
Long International’s detailed schedule  analysis procedure includes  the following steps:
    - Identification of Schedule  Windows
 
    - Correction of the Schedules and Verification of Actual Dates
 
    - Development of a Reasonable As-Planned Schedule for the Start of Each  Schedule Window
 
    - Development of As-Built  Calculation Schedules for Each Schedule  Window
 
    - Preparation of Duration  and Lag Variance Tables
 
    - Identification of Delays  and Allocation of Delay Responsibility
 
    - Schedule Calculations to Determine Delay  Liability
 
A more-detailed discussion of each of these steps is explained  in the following sections.
4.1 IDENTIFICATION OF SCHEDULE WINDOWS
For both the  Update Impacted and the As-Built But-For schedule analyses, Long International  analyzes delays to the Contractor’s work during specific schedule “windows” of  time. This windows approach enables  Long International to assess the dynamic as-built critical path throughout the project as the Contractor’s work was performed and affected by delays. Although performed retrospectively, the  analyses evaluate the effect of delays as they occurred and cumulatively over  the entire period of the project. Typically,  Long International starts with the Contractor’s original planned schedule and  schedule updates to establish the as-planned and as- built schedules during  each schedule window. Using either  each monthly schedule update or combining several consecutive updates to define  a schedule window, Long International establishes the specific window periods  for its analysis based on the data dates of the schedule updates and the timing  of key events during the project that may have caused changes to the critical  path.
4.2 CORRECTION OF THE SCHEDULES
Based on its review of the Contractor’s schedules,  Long International identifies any deficiencies  or errors that, if not corrected, would substantially affect the accuracy of  the delay analysis results. For  example, the Contractor’s schedule updates may contain inaccurate or  inconsistent actual dates. Long  International validates the actual dates in the Contractor’s schedules against  dates recorded in contemporaneous project documentation such as engineering  drawing logs, purchase orders, material receiving reports, daily construction  reports, test reports, punch lists, meeting minutes and monthly progress  reports in order to verify the accuracy of the schedule activity actual  dates. This step ensures that the as-built  schedules accurately reflect  the actual start and  finish dates for completed work activities and properly forecast the critical  path for the remaining work scope.
Common schedule  deficiencies that Long International examines  and corrects include  the following:
      - Incorrect and inconsistent use of as-built  dates;
 
      - Activity planned durations  that are inconsistent with the Contractor’s bid estimate calculations;
 
      - Missing contractual scope of work;
 
      - Lack of contractually required completion activities;
 
      - Over use of constraint dates;
 
      - Missing predecessor or successor logic  ties creating open-end  activities;
 
      - Inadequate   depiction    of    equipment    and    materials procurement and delivery  activities;
 
      - Inaccurate predecessor logic  for Owner approval  activities;
 
      - Lack of a contractual Owner approval period for submittal  and turnover packages;
 
      - Lack of reasonable project punch list and demobilization periods;
 
      - Inconsistent use of Calendars, Progress  Override and Retained Logic schedule calculation options; and
 
      - Unrealistic as-built logic relationships indicating out-of-sequence progress. 
 
After the above schedule deficiencies or errors are corrected, the  Contractor’s as-planned and/or as-built critical path may be different than the  Contractor or Owner thought during the project. Therefore, conclusions  regarding the effect of and responsibility for delays may be different if the  schedule deficiencies or errors were not corrected.
 4.3 DEVELOPMENT  OF A REASONABLE SCHEDULE UPDATE FOR THE START OF EACH SCHEDULE WINDOW
To perform the update impacted schedule analysis, Long  International first ensures that the schedule updates at the start of each  schedule window are reasonable, i.e., the schedule deficiencies identified  above have been corrected. Long  International then uses the scheduling software to recalculate the corrected  schedules to determine: 1) the reasonable baseline schedule at the start of the  project prior to any scope changes or delays, and 2) reasonable schedule  updates that not only identify  consistent and accurate  as-built dates for activities that have started and finished prior to the schedule data date but also correctly  forecast the planned  start and finish dates of  remaining schedule activities at the start of each successive schedule window. These schedule updates represent the  as-planned schedules for the start of each successive schedule window. Figure 5 graphically  depicts the forecast critical path at the start of Window No. 3 of the Olympia  WWTP project schedule analysis. In  this example, the critical path to achieving Final Acceptance by November 7,  2002 is being driven by the delivery of piping materials.
Liquidated damages may apply to not only the project completion date but  also to intermediate milestone activities. Using  the reasonable as-planned schedule at the start of the project and the forecast  schedule updates for the start of each successive schedule window, Long  International sorts and organizes the activity data by float value and/or  longest path to identify the driving paths for each contractually required  milestone date and the overall critical path leading to the project completion  date.
4.4 DEVELOPMENT OF AS-BUILT  CALCULATION SCHEDULES FOR EACH  SCHEDULE WINDOW
To perform  the as-built but-for schedule analysis, Long International prepares an as-built  calculation schedule for each  schedule window. The as-built  schedule window can be defined  as the period of time between  the data dates of two or more successive schedule  updates. The  as-planned schedule update with its data date at the beginning of the schedule  window contains forecast start and finish dates during the schedule window  period. The as-built schedule update  with its data date at the end of the schedule window contains actual start and  finish dates during the schedule window period.
Forecast start and finish dates and float values in a CPM schedule are  driven by the schedule logic and the original or remaining durations of the schedule  activities. When actual dates are  used to update a schedule for work that has started and/or finished during the  as-built schedule window, the actual dates override the schedule logic to fix  the as-built dates of the activities. Therefore, there is no float assigned  to activities having actual finish dates in a statused  schedule. Therefore, the as-built critical path cannot be readily  identified with only the statused schedule containing fixed, as-built dates.
The as-built calculation schedule converts the fixed  as-built schedule dates into calculated early start and early finish dates  based on actual activity durations and as-built logic. The as-built calculation schedule forecast dates are the same as  the as-built schedule dates but are calculated by the scheduling software using  as-built schedule logic and actual activity durations instead of using the fixed actual  dates input to the schedule. For example, as shown in Table 1, the as-built  calculation schedule forecast dates are the same as the as-built schedule  actual dates for Window No. 3. This process  enables Long to determine the actual float values and actual critical and near critical paths during  the as-built period of the schedule. Identification  of delays to the as-built critical path is vital to determine the actual causes  of the delay to the project...
Download PDF to continue reading article, footnotes, figures, tables, and references.
  
 
Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.
Richard J. Long, P.E., is Founder and CEO of Long International, Inc. Mr. Long has over 40 years of U.S. and international engineering, construction, and management consulting experience involving construction contract disputes analysis and resolution, arbitration and litigation support and expert testimony, project management, engineering and construction management, cost and schedule control, and process engineering. As an internationally recognized expert in the analysis and resolution of complex construction disputes for over 30 years, Mr. Long has served as the lead expert on over 300 projects having claims ranging in size from US $100,000 to over US $2 billion. He has presented and published numerous articles on the subjects of claims analysis, entitlement issues, CPM schedule and damages analyses, and claims prevention. Mr. Long earned a B.S. in Chemical Engineering from the University of Pittsburgh in 1970 and an M.S. in Chemical and Petroleum Refining Engineering from the Colorado School of Mines in 1974. 
	©Copyright - All Rights Reserved
	DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.